BuyBloc logo

Infrastructure timeline: Hyderabad

Metro and rail lines, roads and flyovers, water, sewage and power works, hospitals, campuses and new city areas in Hyderabad and the Regional Ring Road belt: when each was announced, approved, begun and opened, as the records show. Every date is as precise as its source gives it, and every stage names its source. A date still to come is a target, with who set it and when; it is not a promise.

What past projects took

Past projects, measured from their own records. Not a forecast for any project.

From first announcement or proposal to opening

  • Railways: 9 years, 1 project
  • Flyovers and underpasses: 5 to 6 years (median 5 years), 2 projects
  • Airports: 8 years, 2 projects
  • Industrial parks: 1 month to 2 years (median 1 year), 2 projects
  • Floods and lakes: 8 months, 1 project
  • Power: 5 years, 1 project
  • Hospitals and health: 4 months to 5 years (median 2 years), 3 projects

12 of the 144 finished projects have both dates in their records; the others are not counted.

First targets for opening

Of 69 projects that reached construction and whose first target date has passed, 64 were not open by it and 5 were.

45 opened after it: under a month to 8 years 2 months (median 9 months) later.

19 were not open as a whole on 16 Oct 2026, 3 months to 6 years 4 months (median 2 years 1 month) after it so far.

How these are counted, and which projects

Measured from past projects' own records, not a forecast for any project. Years to opening: finished projects whose records date both their first announcement or proposal and their opening, each date taken at the middle of the period it can mean. First targets: the first date given for opening, for projects that reached construction, compared with the opening as recorded; a target given for one section is compared the same way, and each record's notes say what each target was for.

Announcement or proposal to opening

  • : 11 Dec 2015 to 6 Jan 2025 (9 years)
  • : 2017 to 1 Jan 2022 (5 years)
  • : 4 Nov 2019 to 28 Jun 2025 (6 years)
  • : 29 May 2000 to 23 Mar 2008 (8 years)
  • : 29 May 2000 to 14 Mar 2008 (8 years)
  • : 8 Jun 2017 to 2017 (1 month)
  • : 2 Mar 2023 to Apr 2025 (2 years)
  • : 14 Nov 2024 to 18 Jul 2025 (8 months)
  • : 4 Jan 2013 to 31 Aug 2017 (5 years)
  • : 10 Apr 2020 to Jul 2020 (3 months)
  • : May 2021 to 15 Nov 2022 (2 years)
  • : 1 Aug 2021 to 17 Aug 2026 (5 years)

First targets by type

TypeDate passedNot open by itOpened later
Metro444 projects, 9 months to 2 years 7 months (median 1 year 7 months) later
Railways886 projects, 1 year to 8 years 2 months (median 4 years 9 months) later
Roads and highways994 projects, 8 months to 1 year 1 month (median 8 months) later
Flyovers and underpasses312822 projects, under a month to 2 years 7 months (median 6 months) later
Airports10-
Industrial parks111 project, 1 year 2 months later
Water supply442 projects, 1 year 6 months to 2 years (median 1 year 9 months) later
Sewage11-
Floods and lakes11-
Hospitals and health442 projects, 6 to 8 months (median 7 months) later
Public buildings and other544 projects, 2 months to 2 years 7 months (median 1 year 3 months) later

Showing 274 projects of 274 · status as of 16 Oct 2026

Announced, proposed, reportApproved, sanctioned, funded, land, tender, awardFoundation stone, works begunOpened, partly opened, completedRevisedStalledTarget (hollow)CancelledDated to the year only

Metro 14

Railways 24

Roads and highways 55

Flyovers and underpasses 84

Airports 5

IT parks 6

Industrial parks 7

City areas and plans 7

Water supply 10

Sewage 3

Floods and lakes 4

Power 6

Hospitals and health 26

Education 11

Public buildings and other 12

How these records are made

BuyBloc compiled one record per project from government releases and orders, parliament replies, agency filings and news reports. A date is never guessed: a stage dated only to the month or the year is shown that way. Where two sources disagree, the record uses the primary one and says so in its notes. A source marked primary is a government body, an agency, parliament or the company building the project; any other is shown as a news report, with its publisher and date. Status is as of the date given with it (16 Oct 2026 for most records).

These are records of what was said and done, not a survey or a legal finding. A project on the map is drawn as BuyBloc’s map layer draws it; check the source for the record itself.

Sources: 493 stages cite a primary source and 920 a news report, from 170 publishers. Cited most: Telangana Today, Deccan Chronicle, Hyderabad Metro Rail Ltd (HMRL), The Hans India, South Central Railway (press release), Ministry of Road Transport and Highways (reply in Parliament), Siasat, The News Minute, The South First, Swarajya, The Siasat Daily, Government of Telangana (press release), Hyderabad Metro Rail Limited, National Medical Commission, The Hindu, Wikipedia, Indian Infrastructure, Government of Telangana (state portal press release), Mission Telangana, The Times of India, Hyderabad Metropolitan Development Authority, National Highways Authority of India, ETV Bharat, Lok Sabha (Digital Library).